Three case studies were completed in order to evaluate the accuracy and applicability of the procedures for evaluating wetland performance. To identify suitable case studies, a number of past permitted projects that included a wetland mitigation component were reviewed. Upon further investigation, three compensatory wetland mitigation projects were selected: 1) Lone Tree Slide/Bolinas Lagoon, in Marin County; 2) Old Salinas River Channel; in Monterey County; and 3) Sweetwater Marsh Complex, in San Diego County. These projects are representative of the type of wetland mitigation projects the CCC receives, and are geographically distributed over a substantial portion of the coastal zone.
The permit files for each wetland mitigation project were reviewed and summarized. A permit review form was used to facilitate the review process. A checklist form was used to determine the extent to which each mitigation plan included the key elements described in this document. The permit review form and the checklist were designed as tools to assist in the preparation and review of coastal development permit applications including compensatory wetland mitigation projects. Blank copies of these forms are included in Appendix A, while completed forms are included as part of each case study.
Current evaluations of the adversely impacted site and the mitigation site were also completed as part of each case study. These evaluations included field inspection of both the affected and mitigation sites, as well as an examination of relevant aerial photos taken in 1986 and 1993. A field evaluation form was completed for each site during the field inspection. A blank copy of this form is included in Appendix A as well, while a completed form is included as part of each case study. Finally, available monitoring reports were reviewed to determine the appropriateness of the monitoring program and to learn how the mitigation sites have changed over time. Information in the monitoring reports and the field evaluation results were used to judge the current level of permit compliance and project performance.
Each case study begins with a background section, which provides a brief project summary. Following the background is a presentation of project specific information organized by the major elements presented in the general procedures for evaluating wetland performance (i.e., (1) ecological assessment, (2) goals, objectives, and performance standards, (3) mitigation attributes, (4) monitoring program, (5) evaluating performance). In the final section of each case study, the general procedures for evaluating wetland performance are used to highlight the strengths and weaknesses of each project. Based on these analyses, possible modifications to the permit language are described.
In January 1991, the Commission approved an application by the California Department of Transportation (Caltrans) to repair a landslide damaged portion of Highway One, south of Stinson Beach in Marin County (Coastal Development Permit 1-90-109). The project resulted in the excavation of the adjacent hillside and subsequent deposition of 201,000 cubic yards of fill into the ocean, covering rocky and sandy intertidal habitat and sandy subtidal habitat immediately below the repair site. Initial deposition and subsequent settling of the fill material resulted in the loss of 5.61 acres of marine habitat. Mitigation was required as a condition of the permit. However, because of the need to repair the road quickly, the CCC expedited the permit process and allowed the preparation and implementation of a compensatory mitigation plan to follow, rather than precede, the repair project. Further, the CCC recognized that "available mitigation sites for in-kind restoration of intertidal or subtidal rocky and beach habitat are limited along the Marin Coast." As a result, "the Commission imposed a condition that allowed some latitude in the development of a restoration plan," to compensate for the direct burial of marine habitat.
The Army Corps of Engineers permit conditions included a requirement that Caltrans coordinate with a multi-agency Technical Advisory Committee (TAC) to develop a mitigation plan for the lost marine habitat. The TAC was composed of staff from fifteen agencies and environmental organizations. Ultimately, a proposal for out-of-kind mitigation at Bolinas Lagoon was recommended by the TAC to fulfill a portion of Caltrans overall mitigation requirement. The Bolinas Lagoon mitigation project (CDP 1-93-07) was approved by the CCC on March 18, 1993. The mitigation project involved the removal of historic fill from two areas in the lagoon, to restore intertidal mudflat habitat and enhance the tidal prism. This project, however, only partially fulfilled Caltrans' mitigation obligation, since only 2.01 acres of lagoon habitat were restored. The remaining 3.6 acres of required mitigation will be satisfied through the restoration of another wetland, Big Lagoon, which is located near Muir Beach, in Marin County. This project is still in the planning stages and will not be addressed in this case study.
Since the Lone Tree Slide site required immediate repairs, no assessment of the impact site (intertidal and subtidal habitat) was performed prior to impact. Thus, the amount and extent of lost habitat and functions are not fully known. However, the chosen mitigation was out-of-kind compensation, so the results of such an ecological assessment could not have been directly applied to the development of appropriate mitigation goals, objectives and performance standards. Instead, a baseline assessment of Bolinas Lagoon was completed prior to construction at the mitigation site. Moss Landing Marine Laboratories produced two monitoring reports in 1992 (MLML, 1992a,b). The reports provide information on species present in the lagoon and state that in areas where there was reduced tidal flushing, there was a reduced density of invertebrates. The Bolinas Lagoon Mitigation Plan produced by Philip Williams and Associates (1992) included information on site analysis, ecological setting, restoration objectives, opportunities and constraints, recommended design, ecological impacts, and the monitoring program.
Additional sampling of nearby reference sites was completed during development of the mitigation plan, to establish the baseline condition for documenting future changes at the mitigation site. This baseline sampling included the collection of information relating to: benthic invertebrates, fishes, birds, mammals, and marsh and upland vegetation. In addition, tide gauges, and channel cross-section transects were established and monitored for characterizing physical baseline conditions.
Information from all of the baseline surveys was used to develop the mitigation plan. From these surveys it was concluded that the most important aquatic community in the study area was the intertidal and subtidal mudflat, whereas the fill areas had minimal habitat value. Therefore, removal of the fill material to increase mudflat habitat and increase the tidal prism was determined to be a "highly positive enhancement of the natural habitat values of the lagoon."
In March, 1993 an assessment of the existing saltmarsh vegetation was performed by Caltrans staff. The purpose of this survey was to identify plant species and determine composition and cover within the existing intertidal marsh zone. This information was used to develop success criteria for the newly created intertidal marsh area after implementation of the mitigation project. This satisfied a permit condition (CDP 1-90-109) that stated success criteria must be established for the saltmarsh portion of the mitigation project, to ensure that the saltmarsh will exhibit species density and diversity similar to the nearby saltmarsh at the same tidal elevation.
The following goals, objectives, and performance standards were established for the Bolinas Lagoon mitigation project (CDP 1-93-07).
Goal:
Create a habitat that functions in a manner similar to a natural mudflat ecosystem in Bolinas Lagoon.
Objectives:
Restore the maximum possible area to intertidal or subtidal habitat
Restore the maximum possible tidal prism to the lagoon
Restore the natural hydrodynamic functioning of the southern portion of Bolinas Lagoon
Encourage the reversal of the process of conversion of mudflats to saltmarsh
Encourage the scouring of deep channels as fisheries habitat
Remove toxic fill from the lagoon.
Performance Standards:
Create 5.7 acre-feet of tidal prism. This was the only performance standard established for evaluating physical success of the project. Monitoring of select physical attributes (e.g., channel elevations, and water level) was used to determine whether this standard was met.
Although performance standards were required for the intertidal saltmarsh fringe plant community, no other biologically oriented performance standards were developed. Based on the existing saltmarsh vegetation survey completed by Caltrans, two success criteria were projected for the newly graded areas adjacent to Highway One: 1) in five years, the saltmarsh vegetation must be established, with 80 percent cover; and 2) all species that are naturally occurring native saltmarsh species (target species) should be evident at the mitigation site by the end of five years. If these target species are not established, remedial action must be taken, including the removal of invasive exotic species. This remedial action is also a specific condition of the permit (CDP 1-90-109).
This project is an out-of-kind compensatory mitigation project, since the restored habitat type is different from the adversely impacted habitat type. The mitigation occurred off-site, as there was no appropriate location close to the impact site.
Calculating a mitigation ratio is more complicated because the Bolinas Lagoon project only fulfills a part of the overall mitigation requirement (i.e., restoration of 2.01 acres). The remaining mitigation requirement will be satisfied upon completion of the Big Lagoon mitigation project. This project is expected to create 2.3 acres of wetland habitat and enhance 13.9 acres of wetland habitat. This combination of compensatory mitigation activities at two different sites will fulfill the mitigation requirement necessary to compensate for the loss of 5.61 acres of marine habitat.
Monitoring of the mitigation site was a specific permit condition (CDP 1-90-109 as amended). This condition required completion of a five-year monitoring program specifically designed to measure the success of the mitigation project.
Monitoring for this mitigation project includes both a physical and biological component. The biological attributes are monitored by Moss Landing Marine Laboratories, while the physical attributes are monitored by Philip Williams, and Associates. The following attributes are being monitored: benthic invertebrates, fish, birds, mammals, marsh and upland vegetation, tidal height, and channel cross-section elevation.
In a subsequent Commission staff report (1992), it was stated that monitoring the physical attributes was expected to determine the following:
the amount of sediment accumulating at the mouth of Stinson Gulch;
the presence of obstructions to andromous fish migrating up Stinson Gulch;
the change in tidal prism; and
the aerial extent of intertidal/subtidal habitat.
Monitoring reports are submitted quarterly; however, data analyses and the performance evaluation are only presented in the annual reports. In December 1994, the CCC received the third quarterly monitoring report (MLML, 1994), which covers the period May 16 through August 10, 1994.
Ecological monitoring for five years was proposed in the Bolinas Lagoon Mitigation Plan. The plan stated that monitoring would be used to document any changes in the ecosystem after project implementation. However, at present only a qualitative evaluation of the mitigation site is possible based on the quarterly monitoring reports and the site inspection completed for this case study. At present, the mitigation site seems to be functioning well. Benthic invertebrates and birds are present in substantial numbers, while the physical information (e.g., channel cross-section and tide gauge data) suggests the lagoon is functioning as a dynamic and tidally influenced system. However, the most recent quarterly report mentions the presence of French broom (Genista sp.) along the roadside adjacent to the mitigation site. The presence of this invasive, exotic plant should invoke the remedial measures described in the performance standards above. Additionally, the most recent monitoring report refers to "foul and stagnant water" in the restoration area, suggesting a lack of tidal flushing. The annual report is expected to provide additional information.
This mitigation project has many merits, most notable, the mitigation work appears to have resulted in restoration of a mudflat area and stands a good chance of being fully successful. In addition, the use of a technical advisory committee to help determine the most appropriate mitigation and to lead the development of a comprehensive mitigation plan was clearly a benefit to this project. However, a review of the procedures described in this document shows there were limitations to the permit, particularly relating to the goals, objectives, and performance standards. Following are some suggested areas for improvement.
This case study illustrates the temporal loss of resources. The construction-related impacts occurred in 1991, while the remaining mitigation is not scheduled to be completed until 1999, when the construction of the Big Lagoon mitigation project is finished. Although an ecological assessment of the impact site was not completed, it seems clear that the interim loss of natural resources is substantial. It is important to fully consider the potential for temporal loss of resources in determining the type and amount of required mitigation. This is particularly important if the mitigation is allowed to follow the impact. One possible way to deal with this issue in a regulatory context is to stipulate a mitigation ratio that could increase over time. For example, suppose the coastal development permit established an initial mitigation ratio of four to one. If the mitigation project was not completed within, say, five years (not including monitoring) then additional mitigation would be required, elevating the overall ratio to five to one. Lack of completion within three more years would lead to additional required mitigation, again elevating the overall mitigation ratio.
A number of baseline surveys of the mitigation site and surrounding area were completed during the development of the mitigation plan for this project. Together, these baseline surveys appear to have functioned as the ecological assessment in terms of developing a strategy for restoration, and to a lesser extent, in developing the goals, objectives, and performance standards. However, a review of the relevant information suggests the baseline survey information would have been more useful if submitted as a single comprehensive document, rather than several separate studies by three different parties completed at three different times. For example, one of the baseline surveys evaluated habitat quality for both benthic invertebrates and fish and concluded that these habitats could be improved through completion of the mitigation project. Subsequently, these habitats were included as part of the mitigation plan and benthic invertebrates and fish are sampled as part of the monitoring program. Yet performance standards for these biotic attributes are not stated, so it is unclear how the monitoring information will be used. This situation illustrates the need to clearly define a process for integrating all of the information necessary to develop a comprehensive mitigation plan before proceeding to implementation. In the case of the Bolinas Lagoon project, the technical advisory committee could have facilitated the synthesis of information from the baseline surveys.
An examination of the goals, objectives and performance standards illustrates an area where modification of the permit conditions could enhance the overall mitigation project. Increasing the tidal prism is a valid performance standard, since information about this change in hydrology will determine, at least in part, whether objectives 2 4 have been met. The tidal prism affects water volume and current speed in the lagoon, which are indicators of the hydrodynamic processes of Bolinas Lagoon. These hydrodynamic processes, in turn, affect the formation of mudflats, channels, and vegetated areas. However, other performance standards exist that, if included, could have allowed for a more comprehensive determination of success. In particular, performance standards could have been included to provide a biological basis for evaluating success. For example, performance standards for benthic invertebrate abundance, shorebird foraging, and shorebird abundance over time all provide information relating to the biological value of the mitigation site. Similarly, the number of fish species and their abundance is an important attribute of the subtidal habitat function and value. Ultimately, a mitigation plan should include performance standards that permit an evaluation of the physical, chemical, and biological attributes important to overall project success.
Table 3 below, lists the goals and objectives stated in the mitigation plan, compared with suggested goals, objectives, and performance standards developed using the information from the baseline surveys and the procedures described in this document.
Several aspects of the mitigation project suggest that concurrent monitoring of nearby reference sites should have been included as part of the monitoring program. First, restoration of Bolinas Lagoon is out-of-kind mitigation. Thus, the ecological assessment consisted of baseline surveys of the mitigation site (before restoration) and the surrounding lagoon. This information was used to develop an appropriate mitigation plan including establishment of the project goals, objectives, and performance standards. Second, the surrounding natural lagoon provides highly appropriate reference sites, so the performance standards could have been linked to the functional level of the adjacent natural lagoon. Establishing the performance standards in this way would provide a mechanism to account for the ongoing natural variability present in the area, resulting in more accurate and realistic evaluations of performance.
Although it is too early to determine the ultimate success of this mitigation project, it does appear the project has a good chance of achieving the stated goals, objectives, and performance standards. More importantly, the site has the potential to provide sustainable, high quality wetland habitat. Yet, as Table 3 illustrates, the determination of project success is largely based on the establishment of physical features and processes. Thus, a full assessment of the biological functioning is not assured. All of the interested parties could benefit from such an assessment.
Table 3. A Comparison of the Goals, Objectives and Performance Standards for the Lone Tree Slide/Bolinas Lagoon Project15
Goals, objectives and performance
|
Suggested goals, objectives
|
|
GOAL: |
GOAL: |
|
1) Create a habitat that functions in a manner similar to mudflat ecosystem in Bolinas Lagoon. |
1) Re-establish the physical processes of natural mudflat habitat in Bolinas Lagoon. |
|
OBJECTIVES: |
OBJECTIVES and PERFORMANCE STANDARDS: |
|
1a) Restore the maximum possible area to intertidal or subtidal habitat. |
1a) Restore the maximum area to intertidal or subtidal habitat.
|
|
1b) Restore the maximum possible tidal prism to the lagoon.
|
1b) Restore the maximum possible tidal prism to the lagoon.
|
|
1c) Restore the natural hydrodynamic functioning of the southern portion of Bolinas Lagoon. |
1c) Restore the natural hydrodynamic functioning of the southern portion of
Bolinas Lagoon.
|
|
1d) Encourage the reversal of the process of conversion of mudflats to saltmarsh. |
1d) Minimize the process of mudflat to saltmarsh conversion.
|
|
1e) Encourage the scouring of deep channels as fisheries habitat. |
1e) Ensure the existence of deep channels for fisheries habitat.
|
|
1f) Remove toxic fill from the lagoon. |
1f) Remove toxic fill from the lagoon.
|
|
|
1h) develop area near mouth of Stinson Gulch to allow unimpeded inflow, while
minimizing sedimentation in the restoration area.
|
|
|
GOAL: |
|
|
2) Re-establish the biological processes of natural mudflat habitat in Bolinas Lagoon. |
|
|
OBJECTIVES and PERFORMANCE STANDARDS: |
|
|
2a) Establish habitat for benthic invertebrates.
|
|
|
2b) Establish habitat for water birds.
|
|
|
2c) Establish habitat for fish.
|
|
PS: 80 % cover of saltmarsh vegetation within five years.
|
2d) Establish appropriate vegetation in mudflat margins.
|
CHECKLIST OF INFORMATION INCLUDED IN THE PERMIT FILE AND THE MITIGATION PLAN FOR THE LONE TREE SLIDE/BOLINAS LAGOON MITIGATION PROJECT
Included |
Omitted |
|
|
X |
Executive Summary | |
Project Description | ||
|
X |
Project location, maps (including aerial photos) | |
|
X |
Project impacts | |
Adversely Impacted Site | ||
|
X |
Ecological assessment of the habitats, functions, and values potentially lost or affected | |
|
X |
Plants (species list) | |
|
X |
Plants (special status species) | |
|
X |
Animals (species list) | |
|
X |
Animals ( special status species) | |
|
X |
Exotic Species (plant and/or animal) | |
|
X |
Water regime/Hydrology | |
|
X |
Water quality | |
|
X |
Soils/Substrate | |
|
X |
Buffers/Surrounding Habitats/Surrounding Land Use | |
Mitigation Goals, Objectives, and Performance Standards | ||
|
X |
Specific Goals (statements of project purpose and expected outcome) | |
|
X |
Specific Objectives (specific actions, or steps taken to achieve the goals) | |
|
X |
Performance standards: quantitative criteria to assess the attainment of goals/objectives | |
|
X |
Time frame: statement of period over which attributes must be shown to be present | |
|
Mitigation Site | ||
|
X |
Ecological assessment of the existing habitats, functions, and
values potentially lost | |
|
X |
Salvage plan (conserves plants and animals from the affected and/or mitigation site) | |
|
X |
Site description, project concept drawing | |
|
X |
Design Rationale | |
Site Plan and Design | ||
|
X |
Site survey and topography | |
|
X |
Specific
design elements and construction methods for hydrology | |
|
X |
Specific design elements and
construction methods for soil | |
|
X |
Specific design elements and
construction methods for ground elevation changes | |
|
X |
Specific design elements and construction methods for buffer areas | |
|
X |
Specific design for vegetation (species composition, exotics removal, sources of seeds) | |
|
X |
Potential Problems and Remedial Measures (responsible entity) | |
|
X |
Long-term Maintenance requirements | |
Monitoring Program | ||
|
X |
Hydrology | |
|
X |
Soils | |
|
X |
Water quality | |
|
X |
Plants | |
|
X |
Animals | |
|
X |
Success
criteria for physical and chemical attributes | |
|
X |
Success criteria for biological
attributes
| |
|
X |
Timetable for reporting monitoring results | |
Implementation Schedule | ||
|
X |
Construction schedule | |
|
X |
Monitoring schedule |
LONE TREE SLIDE/BOLINAS LAGOON PERMIT FILE REVIEW
|
PERMIT NUMBER: 1-93-07 (1-90-109 as amended) |
APPLICANT: Calif. Dept. of Transportation |
STAFF ANALYSTS: Strachan, Merrill, Scholl |
|
PERMIT APPROVAL DATE: January 1991 |
PROJECT START DATE: July 1991 |
PROJECT COMPLETED DATE: January 1993 |
|
Wetland Mitigation project: (X) Yes ( ) No |
Wetland Restoration project: ( )Yes ( ) No | |
LOCATION OF ADVERSELY IMPACTED SITE Pacific Coast Highway | COUNTY: Marin | CITY: Stinson Beach |
DESCRIPTION OF AREA AFFECTED: 5.61 acres of rocky intertidal habitat, sandy subtidal habitat, localized water column affected from erosion of fill material | ||
LOCATION OF MITIGATION/RESTORATION SITE: Bolinas Lagoon | COUNTY: Marin | CITY: Stinson Beach |
ACRES MITIGATED OR RESTORED: 2.01 | ||
|
SUMMARY OF PROJECT, INCLUDING WETLAND ACRES, HABITATS, AND FUNCTIONS AFFECTED AND PROPOSED MITIGATION: In January 1991, the Commission approved an application by the California Department of Transportation (Caltrans) to repair a landslide damaged portion of Highway One, south of Stinson Beach in Marin County, permit number 1-90-109. The project resulted in the excavation of the adjacent hillside and deposition of 201,000 cubic yards of fill into the ocean, covering rocky and sandy subtidal and intertidal habitat below the repair site. Initial deposition and subsequent settling of the fill resulted in the loss of 5.61 acres of marine habitat. Mitigation was required as a condition of the permit, however, because of the need to repair the road quickly, the Commission expedited the permit process and allowed the preparation and implementation of the mitigation plan to follow, rather than precede, the repair project. As available mitigation sites for in-kind restoration of intertidal and subtidal rocky and sandy habitat are virtually nonexistent along the Marin County coast, the permit condition allowed for some latitude in the development of a mitigation plan to compensate for the direct burial of marine habitat. As a result, compensatory mitigation focused on opportunities for off-site, out-of-kind mitigation. To address the mitigation condition, Caltrans utilized a Technical Advisory Group to review various mitigation proposals. Ultimately, restoration of a portion of Bolinas Lagoon was selected to satisfy part of the total mitigation requirement. The Bolinas Lagoon mitigation project was permitted on March 18, 1993 (CDP 1-93-07), and involved the removal of historic fill from two areas in the lagoon to restore intertidal mudflat habitat and enhance the tidal prism. This project, however, only partially fulfilled the mitigation requirements, since only 2.01 acres of lagoon habitat were restored. The remaining 3.6 acres of required mitigation will be satisfied at another wetland, Big Lagoon, which is located near Muir Beach, in Marin County. This portion of the mitigation requirement is still in the planning stages and will not be addressed in this file review. | ||
Mitigation Attributes:
|
TYPE OF MITIGATION PROJECT: (X) Restoration ( ) Creation ( ) Enhancement ( ) In-kind (X) Out-of-kind |
|
ACREAGE FOR EACH TYPE IF MORE THAN ONE : 2.01 acres of intertidal mudflat and marsh habitat |
|
|
MITIGATION CONDUCTED: ( ) On-site (X) Off-site |
IF OFF-SITE, RELATIVE LOCATION OF IMPACT SITE VS. MITIGATION SITE (I.E., JURISDICTION, WATERSHED, ETC.): Within the same county, different watersheds, different habitats |
MITIGATION RATIO ACRES MITIGATED: ACRES AFFECTED 2.01 : 5.61 = 0.36 : 1 (The remaining 3.6 acres to be satisfied at Big Lagoon) |
IS PRESERVATION/ACQUISITION A PROJECT COMPONENT? ( ) Yes (X) No |
IF YES, DESCRIBE WHAT IS BEING PRESERVED OR ACQUIRED, WHERE IT IS LOCATED, THE COSTS AND FUNDING SOURCES AND WHO WILL ASSUME RESPONSIBILITY: |
WAS THERE AN ECOLOGICAL ASSESSMENT OF THE ADVERSELY IMPACTED SITE BEFORE CONSTRUCTION OR ALTERATION? ( ) Yes (X) No |
IF SO, LISTS THE REPORTS, CONCLUSIONS OF THE SITE EVALUATION: |
WAS THERE AN ECOLOGICAL ASSESSMENT OF THE MITIGATION SITE BEFORE CONSTRUCTION OR ALTERATION? (X) Yes ( ) No |
|
IF SO, LISTS THE REPORTS, CONCLUSIONS OF THE SITE EVALUATION: Moss Landing Marine Laboratories produced two reports in 1992 that contain baseline information. Also in 1992, Philip Williams and Associates completed the Bolinas Lagoon Mitigation. These reports emphasized the value of the mudflat habitat, and the positive habitat values which would result from increased tidal prism. In 1993, Caltrans completed an assessment of existing saltmarsh vegetation. |
WAS THERE AN ECOLOGICAL ASSESSMENT OF A REFERENCE SITE BEFORE CONSTRUCTION OR ALTERATION? ( ) Yes (X) No |
|
IF SO, LISTS THE REPORTS, CONCLUSIONS OF THE SITE EVALUATION: |
WERE GOALS AND OBJECTIVES LISTED IN THE APPLICATION MATERIALS? (X) Yes ( ) No |
|
IF SO, LIST THE GOALS AND OBJECTIVES: |
|
GOAL: Create a habitat that functions in a manner similar to natural mudflat habitat in Bolinas Lagoon. |
OBJECTIVES:
|
|
WERE PERFORMANCE STANDARDS FOR ASSESSING ATTAINMENT OF EACH GOAL/OBJECTIVE LISTED? (X) Yes ( ) No (Yes, but not for each objective) |
|
IF SO, LIST THE PERFORMANCE STANDARDS, OR SUCCESS CRITERIA: The creation of 5.7 acre-feet of tidal prism will establish physical success of the project. 80% cover of saltmarsh vegetation required after 5 years on the graded area along Highway One. |
WAS A MONITORING PROGRAM INCLUDED? (X) Yes ( ) No (The monitoring was required as a condition of the Coastal Development Permit, to ensure the project was a success and that it provides adequate mitigation.) |
LENGTH OF MONITORING PROGRAM: 5 years |
|
WHEN ARE MONITORING REPORTS DUE? Quarterly |
|
BRIEFLY LIST THE PARAMETERS TO BE MONITORED: Benthic invertebrates, fishes, birds, mammals, vegetation, tide height, and channel cross-section elevation surveys. |
EVALUATION OF PERFORMANCE: |
DO SUCCESSIVE MONITORING REPORTS DOCUMENT PERFORMANCE OF THE PROJECT? ( ) Yes (X) No |
|
IF YES, DOES THE DATA INDICATE THAT THE SYSTEM IS EVOLVING TO MEET THE GOALS, I.E., IS THE PERFORMANCE IMPROVING? In December, 1994, the Commission received the Third Quarterly Report of the long-term monitoring of post-construction conditions at Bolinas Lagoon for the period May 16 through August 10, 1994. Based on this report the site seems to be functioning well; benthic invertebrates are found in sufficient numbers, as are birds, the physical cross-sections of the lagoon reveal a dynamic and tidally influenced system. The annual report will evaluate performance. |
LONE TREE SLIDE/BOLINAS LAGOON MITIGATION SITE EVALUATION
|
DATE OF VISIT: 12 / 7 / 94 |
EVALUATORS: Merrill, Hymanson, Kingma |
Fill in this portion of the form before the site visit
Project Information:
PROJECT NAME: Highway One Lone Tree Slide Repair, Bolinas Lagoon, and Big Lagoon Restoration Projects. | |||
|
PERMIT NUMBER: 1-93-07 (1-90-109 as amended ) |
ANALYSTS: Strachan, Merrill, and Scholl | ||
|
MITIGATION PROJECT LOCATION: Bolinas Lagoon |
CITY: Stinson Beach |
COUNTY: Marin | |
|
|
|
| |
PERMIT APPROVAL DATE: 1 / 11 / 91 |
CONSTRUCTION START DATE: 7 / 91 |
PROJECT COMPLETION DATE: 12 / 93 | |
|
(X) Mitigation or ( ) Restoration | |||
|
IMPACT AREA: Acres: 5.61 | |||
|
HABITAT TYPE: Rocky intertidal, sandy intertidal, local water column | |||
|
MITIGATION SITE: | |||
|
Acres: | ENHANCED: |
RESTORED: 2.01 | CREATED: |
|
Habitat type: |
Mudflat and fringe salt marsh | ||
|
RESTORATION SITE: | |||
|
Acres: | ENHANCED: |
RESTORED: |
CREATED: |
|
Habitat type: | |||
|
PROJECT GOALS AND OBJECTIVES (AS STATED IN THE FILE DOCUMENTS) | |||
|
GOAL: Create a habitat that functions in a manner similar to natural mudflat ecosystems in Bolinas Lagoon. | |||
OBJECTIVES:
| |||
|
WERE PERFORMANCE STANDARDS FOR ASSESSING ATTAINMENT OF EACH GOAL / OBJECTIVE LISTED? Yes, but not for each objective | |||
IF SO, LIST THE PERFORMANCE STANDARDS, OR SUCCESS CRITERIA: The creation of 5.7 acre-feet of tidal prism will establish physical success of the project. 80% cover of saltmarsh vegetation required after 5 years on the graded area along Highway One. | |||
|
WAS A MONITORING PROGRAM INCLUDED? Yes, the monitoring was required as a condition of the coastal development permit to ensure project success and to ensure the provision of adequate mitigation. | |||
|
LENGTH OF MONITORING PROGRAM: 5 years | WHEN ARE MONITORING REPORTS DUE? Quarterly | ||
|
BRIEFLY LIST THE PARAMETERS TO BE MONITORED: Benthic invertebrates, fishes, birds, mammals, vegetation, tide gauges, and physical cross-section elevation surveys. | |||
|
EVALUATION OF PERFORMANCE BASED ON THE MONITORING REPORTS: | |||
|
DO SUCCESSIVE MONITORING REPORTS DOCUMENT PERFORMANCE OF THE PROJECT? ( ) Yes (X) No | |||
IF YES, DOES THE DATA INDICATE THAT THE SYSTEM IS EVOLVING TO MEET THE GOALS, I.E., IS THE PERFORMANCE IMPROVING? In December, 1994, the Commission received the Third Quarterly Report of the long-term monitoring of post-construction conditions at Bolinas Lagoon for the period May 16 through August 10, 1994. Based on this report the site seems to be functioning well; benthic invertebrates are found in sufficient numbers, as are birds, the physical cross-sections of the lagoon reveal a dynamic and tidally influenced system. The annual report will evaluate performance. | |||
Fill in this portion of the form during the site visit
|
PHOTOS TAKEN? Yes, includes photos of the adversely impacted site, the mitigation site at Bolinas Lagoon, and the proposed mitigation site at Big Lagoon. |
Habitat Characterization:
ADVERSELY IMPACTED SITE : | |
VEGETATION TYPES Grasses, and exotic plants: pampas grass at fill area | |
|
PERCENT COVER VEGETATION 70 80% |
PERCENT OPEN WATER: Not Applicable |
|
CURRENT CONDITION: Unstable with evidence of erosion, subsidence, and sediment plume | |
|
ADDITIONAL COMMENTS: (E.G., BIRDS FEEDING, ETC.) The fill is slumping and shows signs of instability. Annual grasses cover much of the fill, however, the cut area is mostly unvegetated and erosion is evident. Evidence of deer and rodents. | |
|
MITIGATION SITE: | |
VEGETATION TYPES Pickleweed and bulrush (along fringe of marsh) | |
|
PERCENT COVER VEGETATION: <10%: mostly mudflats | PERCENT OPEN WATER: >90% at high tide |
MAINTENANCE STRUCTURES: Sediment trap, stream culvert | |
|
EVIDENCE OF CONSTRUCTION: Some tire tracks and grading marks evident. Sediment appears to be courser in certain areas | |
ADDITIONAL COMMENTS: (E.G., BIRDS FEEDING, MAMMALS SEEN, OBSERVED DETRIMENTS TO WATER QUALITY, ETC.) High abundance of water birds on mudflats. Many species seen foraging: Willets, Avocets, Mallards. High abundance of snails on the mudflats. Bulrush and pickleweed growing at edge.. | |
Fill in this portion of the form after the site visit
|
BASED ON THE SITE EVALUATION, DOES THE MITIGATION OR RESTORATION WETLAND PERFORMANCE APPEAR TO BE ( ) increasing? or ( ) decreasing? or (X) mixed? |
|
WHY? The mitigation site appears to be performing well since it is providing foraging habitat for shorebirds and other water birds. The invertebrates appear to be thriving in the environment, and tidal water flow was evident. The performance standard for tidal prism cannot be evaluated by a site visit; however, over time the vegetation and presence of wildlife will indicate if the restored area is functioning in a manner similar to the reference sites in the Bolinas Lagoon. The performance standard for saltmarsh vegetation cover and species composition has not been met: exotic plant species were noted and plant cover in some areas is less than 80%. |
DO CONDITIONS EXIST THAT REQUIRE REMEDIAL ACTION (E.G., REPAIR A MAINTENANCE STRUCTURE)? ( ) Yes (X) No |
|
REMEDIATION FOLLOW-UP Not applicable |
ADDITIONAL COMMENTS: None |
In 1988 The Moss Landing Harbor District (hereafter referred to as the Harbor District) applied for a coastal development permit to construct a 1,300 foot-long bulkhead along the west bank of the south harbor, near Sandholdt Road in Moss Landing. The proposed construction involved the placement of 5,500 yards of rock rip-rap for shoreline protection, along with associated demolition, dredging, fill, and spoils disposal. As proposed, the project would adversely affect approximately 0.35 acre of mudflat habitat. The project was determined to be consistent with the Coastal Act and a coastal development permit (CDP 3-88-47) was issued. However, the CCC required the Harbor District to submit a mitigation plan to compensate for the adverse impacts from the bulkhead construction. The permit conditions included several specific requirements regarding the mitigation plan, which are discussed later in this write-up.
In June 1988, a "stop work" order was issued to the Harbor District by the CCC for unauthorized grading and filling of a wetland along the Old Salinas River just south of the bulkhead site. Specifically, three acres of old dredge ponds and adjacent berms were re-graded in order to level the area. Additionally, several truckloads of trash were removed from an area occupied by transients. This activity was considered a violation because no coastal development permit or Section 404 permit had been issued for this work, as required by the Coastal Act and the Clean Water Act respectively. The Army Corps of Engineers (COE) determined that 1.4 acres of the graded area had been jurisdictional wetland under Section 404 of the Clean Water Act. Subsequently, all activities related to the bulkhead project were suspended in June 1988. In order to resolve this violation and complete construction of the bulkhead, the Harbor District was required to mitigate for the unauthorized activities by fully restoring the lost wetland habitat. In addition, the site of the unauthorized activities was identified as a possible mitigation site for the adverse impacts associated with the bulkhead construction.
In 1989, Jones and Stokes Associates completed the Moss Landing Harbor Wetland Mitigation Plan. This plan proposed compensatory mitigation for the loss of 0.35 acre of mudflat habitat at the bulkhead site and mitigation (via restoration) for the unauthorized filling of 1.4 acres of jurisdictional wetland. Mitigation for both activities was proposed to occur at the unauthorized fill site adjacent to the Old Salinas River. The mitigation plan addressed the conditions of the coastal development permit, outlining the proposed restoration activities at the fill site. The mitigation plan was approved in October 1989. In 1990, the Habitat Restoration Group completed the Revegetation and Monitoring Program for Moss Landing South Harbor Restoration Project, which further described the activities proposed at the mitigation site. This report also outlined the monitoring program that would be used to document mitigation project performance.
Relatively speaking, a great deal of work was completed to assess the functions and values of both the adversely impacted and the mitigation sites. Between 1985 and 1989 four separate studies were completed, each of these is described below.
In 1985, an intertidal invertebrate study was completed as part of the application process for the coastal development permit to construct the bulkhead (Fukuyama, et al., 1985). For this study both sites in the project area and adjacent control plots were sampled concurrently in order to compare the habitat quality of the proposed bulkhead site to adjacent natural intertidal areas. This study found that the area was extensively modified by human activities and contained relatively few invertebrates. Additionally, an environmental assessment of the proposed bulkhead site was performed by the Army Corps of Engineers (COE, 1988), in which the potential effects to the construction site were described. The assessment determined the elevation and substrate composition of existing subtidal and intertidal habitat would be altered, and there would be an increase in turbidity in the affected area. The bulkhead construction activities were anticipated to adversely affect the intertidal mudflats, and result in the loss of aquatic habitat important to estuarine and invertebrate species.
One of the coastal development permit conditions required "a pre-construction survey of intertidal habitat to be lost" (CDP 3-88-47). In 1988 an expanded initial study was conducted for the bulkhead site (John Gilchrist and Associates, 1988). Field sampling characterized the proposed bulkhead site as rocky to silty-sand substrate with accumulations of human generated debris. This report included an invertebrate study, which concluded that "although diversity was relatively high, low species density indicates that this is not high quality habitat." Further, this report concluded that adverse impacts to the benthos and the fish would occur as a result of the increased sedimentation and turbidity in the construction area. Meanwhile, the proposed dredging would result in the direct burial of benthic organisms. No ecological assessment of the violation site was performed prior to the unauthorized grading and filling activity.
The Mitigation Plan (Jones and Stokes, Associates 1989) provided a characterization of the affected areas, and described the condition of both the bulkhead and the unauthorized fill sites prior to impact. The pre-impact conditions at the unauthorized fill site were generally described as having contained areas of undisturbed tidal saltmarsh and moderately disturbed marsh and upland. Common plants at the site included pickleweed, saltgrass, and other marsh vegetation. This compliment of vegetation remains in relatively large areas of high quality saltmarsh immediately south of the violation site and elsewhere in the vicinity. Common mammals and birds likely to have used the site were also listed. Overall, characterization of the bulkhead site in the mitigation plan concurred with earlier ecological assessments of the intertidal habitat, although a discontinuous band of disturbed saltmarsh and upland vegetation was also reported to exist at the bulkhead site.
A single ecological assessment of the adversely impacted and mitigation sites was not completed. However, results of the four studies described in the section above provide comparable information that was used to develop the goals, objectives and performance standards for this mitigation project.
The goals for this project are best described in the 1990 report, written by the Habitat Restoration Group:
To establish salt marsh vegetation on the project site that is virtually and ecologically similar to the adjacent undisturbed areas.
To begin a process of succession that will result in habitat and wildlife values similar to neighboring undisturbed saltmarsh areas.
To return the area to a stable ecosystem which will require no further human input once the vegetation has been established.
The objectives for the project are clearly stated in the 1989 Mitigation Plan written by Jones and Stokes Associates:
Restore approximately 1.4 acres of saltmarsh habitat in the area impacted by grading and fill deposition. The restored saltmarsh would provide one to one compensation (on an aerial basis) for the fill material deposited in the wetland.
Create at least 1.05 acres of tidal mudflat habitat in the area disturbed by grading. The new mudflat would provide three to one compensation for the filling of approximately 0.35 acre of mudflat at the proposed bulkhead site.
Create wetland habitat values at the mitigation site that are equal to or greater than those lost at both sites. Net increases in habitat values could compensate for temporary losses in wetland values over several months.
Re-create and improve the upland buffer around the restored wetlands. Upland buffers would provide refuge for saltmarsh animals during periods of high water and would reduce disturbance to wetland wildlife from activity in surrounding developed areas.
Performance standards "to determine successful revegetation of the area and a plan outlining where, when, and how additional areas would be enhanced if the mitigation was not successful" were required in the coastal development permit. The mitigation plan (Jones and Stokes Associates, 1989) provided specific performance standards:
Mudflats: Mudflats in the mitigation area should remain largely unvegetated, open to daily tidal flows from the Old Salinas River, and free of ponded water during low tides. Within 25 years after completion of grading, mudflats in the mitigation area should achieve an appearance and level of shorebird use similar to those of mudflats in the old Salinas River.
Pickleweed Marsh: Natural establishment of pickleweed should be evident on the marsh plain area within one year after grading is completed. Significant increases in pickleweed cover should be evident in each succeeding year. After five years, vegetation in the pickleweed marsh should be dominated by pickleweed and have achieved (or exhibit a trend toward) percent cover that is comparable to that in undisturbed pickleweed marshes along the Old Salinas River.
Saltgrass Marsh: Survival and establishment of saltgrass should be evident in planted areas within two months after planting is completed. Significant increases in saltgrass cover should be evident in each succeeding year. After five years, vegetation in the saltgrass marsh should be dominated by saltgrass and have achieved (or exhibit a trend toward) percent cover that is comparable to that in undisturbed saltgrass marshes along the Old Salinas River.
Peripheral Upland: Survival and establishment of upland plants should be evident in planted areas within 2 months after planting is completed. A significant increase in upland plants should be evident in each succeeding year. After five years, vegetation in the upland should be dominated by native shrubs and provide substantial visual screening from nearby buildings, yards, and human activity.
The mitigation plan (Jones and Stokes Associates, 1989) also described the remediation requirements if these standards were not met:
Mudflats: If significant ponding or blockage of the slough entrances occurs, the slough channels will be deepened or otherwise modified as necessary to improve the flow of water. If the mudflats do not function similarly to those in the Old Salinas River after five years, the performance standards will be reassessed and other remedial actions may be identified in consultation with COE and other commenting agencies.
Pickleweed Marsh: If natural establishment of pickleweed is not evident within one year and if habitat conditions appear suitable for this species, seed-bearing stems will be collected from a nearby marsh and scattered throughout the area intended for pickleweed establishment. If annual increases in pickleweed cover appear to be inadequate, soil salinity, fertility, and moisture conditions will be examined and fertilizers or freshwater irrigation will be applied, if necessary. If pickleweed cover is inadequate and does not exhibit an increasing trend after five years, the performance standards will be reassessed and other remedial actions may be identified in consultation with COE and other commenting agencies.
Saltgrass Marsh: If saltgrass plantings fail to survive in portions of the planted area, additional plugs or transplants will be planted to replace those lost. If annual increases in saltgrass cover appear to be inadequate, soil salinity, fertility, and moisture conditions will be examined and fertilizers or additional irrigation will be applied, if necessary. Additional plants of other native species appropriate to this habitat may be planted. If saltgrass cover is inadequate and does not exhibit an increasing trend after five years, the performance standards will be reassessed and other remedial actions may be identified in consultation with COE and other commenting agencies.
Peripheral Upland: If upland plantings fail to survive in portions of the planted area, additional plants will be planted to replace those lost. If annual increases in cover appear to be inadequate, soil salinity, fertility, and moisture conditions will be examined and fertilizers or additional irrigation will be applied, if necessary. Additional plants of other native species appropriate to this habitat may be planted. If visual screening is inadequate and does not exhibit an increasing trend after five years, the performance standards will be reassessed and other remedial actions may be identified in consultation with COE and other commenting agencies.
Additionally, the 1990 report by the Habitat Restoration Group stated "a success criteria of 90 percent survival after one full year of growth after installation shall be established for all installed plants." This applies to all the plant types mentioned above.
Mitigation for all adverse impacts occurred at the unauthorized fill site. The mitigation plan stated that "combining restoration of the two different habitats at one location will provide a more complete and diverse ecosystem that is expected to have higher habitat qualities than either impact area prior to disturbance." Combining these two mitigation requirements on one site seemed the most logical approach, given the type and proximity of the adverse impacts and the land ownership of the harbor district. However, this decision necessitated a mitigation plan that provided in-kind mitigation for both vegetated saltmarsh and mudflat habitats at a single site. The approach described in the mitigation plan was "to excavate most of the disturbed area [the unauthorized fill area] to elevations below pre-disturbance levels to increase the amount of tidally influenced low saltmarsh and mudflat habitats. Some existing uplands would be converted to wetlands by ... excavating part of the upland at the north end of the site." Thus, partial restoration of the saltmarsh and partial conversion to provide mudflat habitat occurred in an area that had previously existed as vegetated saltmarsh. In addition, some new wetland habitat was created in previously upland areas. This suggests the overall project included some wetland restoration, some wetland conversion (considered enhancement) and some wetland creation.
A condition of the coastal development permit required a "mitigation site replacing lost intertidal habitat with like habitat at a 3 to 1 ratio." Therefore, the 0.35 acre of mudflat lost at the bulkhead site required 1.05 acres of mudflat habitat as mitigation. In fact, the mitigation project resulted in 1.1 acres of mudflat habitat, yielding a final mitigation ratio of approximately 3.1 to 1. Mitigation for the 1.4 acres of saltmarsh impacted by the unauthorized grading and fill yielded a 1 to 1 mitigation ratio. The combined mitigation ratio was somewhat greater than 1 to 1 and resulted in a net increase of mudflat habitat, although at the expense of vegetated saltmarsh habitat (Table 4).
Table 4. Summary of Applicable Acreage Values and Resulting Mitigation Ratio for the Moss Landing South Harbor Mitigation Project
Habitat | Acres | |||
Mitigated | Lost | Ratio |
Net Change | |
|
Mudflat |
1.1 |
0.35 |
3:1 |
+ 0.75 |
|
Saltmarsh |
1.4 |
1.4 |
1:1 |
0.00 |
|
Combined |
2.5 |
1.75 |
1.4:1 |
+ 0.75 |
Another condition of the coastal development permit was that "mitigation project construction occur concurrently with the bulkhead project." This is an important consideration, because it minimizes the temporal loss of wetland habitat. Although settlement of the unauthorized activities delayed both the mitigation and bulkhead work, eventually all work did proceed concurrently.
An additional condition of the coastal development permit was that "a five year monitoring program with annual reports, prepared by a qualified biologist, be submitted to the Executive Director and the Department of Fish and Game." The mitigation plan stated that monitoring will "evaluate whether the restored habitats are progressing toward the mitigation objectives." The Habitat Restoration Group's (1990) report stated that "the goals of the monitoring program are to measure success of the [mitigation] project, to evaluate the extent to which restoration of an entire ecosystem is established, and to determine additional needs or inputs, such as replanting, or controlling undesirable plants..."
The mitigation plan suggested the following monitoring program, with vegetation as the primary attribute of the monitoring activities. Vegetation cover and composition throughout the site would be recorded at two month intervals for the first year, then twice a year for the next four years. The locations of naturally establishing pickleweed will be mapped. The identity and relative abundance of all plants will be recorded. Plant composition and percent cover will be surveyed in ten permanent 1-meter square vegetation plots. Potential problems that may require remediation will be monitored, such as erosion, or failure of plants to become established. As previously mentioned, the mitigation plan provided specific requirements for remediation should the mudflat, pickleweed, or saltgrass habitat fail to become established. The monitoring reports were expected to document when these remedial measures should be considered. The monitoring program also included periodic monitoring to determine the species richness and abundance of birds and benthic fauna at the mitigation site over time.
Unfortunately, assessing this project on the basis of the monitoring reports does not provide a complete understanding of the condition of the mitigation site. Monitoring reports for the first two years, 1991 and 1992, were produced by The Habitat Restoration Group. ( A discussion of the results of these two reports will follow.) Monitoring of the site was interrupted after 1992 due to procedural difficulties within the Harbor District in establishing a new contract for monitoring. Assegued and Associates was ultimately awarded the monitoring contract and submitted a progress report in 1994; however, the third annual monitoring report is still pending. Monitoring is expected to continue at least until 1996, unless remedial action is taken, which could extend the monitoring program.
The goals and objectives of this project suggest the mitigation site will be restored to a condition similar to the adjacent natural marsh. These goals indicate that concurrent monitoring of both the mitigation site and adjacent reference sites is necessary. The 1991 monitoring report documents the monitoring of control plots for just such a purpose. Bird surveys were completed at both the mitigation site and adjacent control sites. Benthic invertebrates were sampled at the mitigation site and control sites across the channel. The same comparison with a reference area (i.e., undisturbed marsh habitat) was to occur for the vegetation monitoring as well; however, no reference site information is presented in any of the reports on file.
The appendix of the Habitat Restoration Group's report (1990) characterizes bird usage at the mitigation site based on the preliminary results of bird monitoring. It is concluded that "waterbird species richness on the [mitigation] site is greater than elsewhere along the Old Salinas River." These results are corroborated in the 1991 monitoring report (The Habitat Restoration Group, 1991). This monitoring report also states that the abundance of benthic organisms on the mitigation site approximates abundance levels documented in nearby control sites. The 1992 monitoring data for shorebirds indicates the mitigation site has high habitat value as a forage area for birds (The Habitat Restoration Group, 1992). While results from the 1994 progress report (Assegued and Associates, 1994) for these two biotic attributes are inconclusive, the CCC staff's site evaluations in December 1994 and February 1995, corroborated earlier findings that the restored mudflat provides good habitat for shorebirds.
No trend is evident in the establishment of vegetation at the mitigation site. The first monitoring report in 1991, does not present vegetation data recorded at two month intervals, as stipulated in the 1990 mitigation plan. Only four data sets are available between May 1990 and June 1991. This data shows that while some areas of the mitigation site have relatively high vegetation survival rates and recruitment, the southern portion of the site experienced die-off and slower rates of growth. Thus, at least some areas of the mitigation site did not meeting the 90 percent success criteria for installed plants. These results may be due to the presence of unsuitable substrate, specifically the dredge spoil material used to construct portions of the site.
The 1991 monitoring report states that "no plant or natural species recruitment occurred during the first year on the eastwest arm extending towards the Old Salinas River. The absence of any species colonization in this area is difficult to explain." These statements suggest the project was not performing as expected, and raises concerns for condition compliance. This type of information should trigger staff investigations into remediation.
In 1992 the vegetation monitoring regime was changed. As a result, the vegetation data was analyzed on a community level basis rather than a species specific basis as presented in the 1991 monitoring report. These differing methodologies prevent direct quantitative comparisons between years. The 1992 vegetation data indicates a relative increase in plant cover and establishment. In some areas, however, much of the increase in plant cover can be attributed to non-native species, which suggests a decline in habitat value. Overall, it was concluded from the 1992 monitoring data that no additional work in the vegetated areas, other than weeding, would be required. Although the associated vegetation data seems to support this conclusion, the CCC staff's site evaluation in December 1994 (see attached form), raises questions about the validity of this conclusion.
The 1994 progress report (Assegued and Associates, 1994) states that vegetation at the mitigation site shows "very high survival rates throughout the restored site... Overall almost complete coverage of the restored area by native species was noted..." However, both the CCC staff's site evaluation and aerial photos taken in 1993, show that significant portions of this site lack vegetation. This is partially due to the presence of an incised channel, which was first reported in the 1992 monitoring report. By 1994, the incised channel had created a mudflat island of the "arm" extending toward the center of the Old Salinas River. A subsequent site inspection by CCC staff in February 1995 showed the incised channel had deepened and widened with the previous winter storms, and tidal currents appear to have further eroded the newly formed mudflat island. The absence of vegetation on this island and surrounding mudflat areas was evident during the site visit, and is not consistent with the expected vegetation distribution described in the revegetation plan. In addition, an ongoing transition of intertidal to subtidal habitat appears to exist, which is also not consistent with the expected habitat distribution.
This mitigation project has many merits and includes many of the features necessary for a project to achieve a high degree of success, as described in this guidance document. For example, this project had an ecological assessment of the bulkhead site prior to impact, and a habitat characterization of the unauthorized fill site. This information relates to the habitat functions and values that require mitigation, and is reflected in the goals, objectives, and performance standards. The mitigation attributes of this project address the need to compensate for lost habitat either by increasing the ratio, or by directly compensating for the resources through on-site restoration of in-kind habitat. In addition, interim losses of wetland habitat were minimized through a permit condition that required the mitigation to be completed concurrent with the bulkhead construction. The monitoring program was designed to determine whether the performance standards have been met, and if the mitigation site is progressing toward functional equivalency with the adjacent natural saltmarsh.
The permit conditions and the mitigation plan provided for remediation if necessary. The monitoring reports were intended to document any potential problems at the site that may require remediation. However, despite these permit conditions and the regulatory actions required for the associated violation, the CCC did not require remediation when the site failed to perform as expected. The apparent change in hydrology at the site, which has resulted in a deep incised channel and a relative increase in unvegetated area, should have been addressed in 1992 when it was first described in the monitoring report. The coarse fill material, which appears to have precluded the establishment of vegetation in certain areas of the site, could have been amended with more appropriate material. These features could have been addressed more directly if there had been performance standards for the physical and chemical attributes of this project. For example, a performance standard for the sediment could have read: sediment composition at the mitigation site must achieve (or exhibit a trend toward) the composition of sediment found in nearby reference site within five years.
The resulting functions of the mitigation site are largely a product of the project design. In retrospect, however, it appears that it was inappropriate to create mudflat habitat in an area that was historically vegetated saltmarsh. The continued habitat instability at the site, marked by enlargement of the incised channel and erosion of the intertidal mudflat, are direct evidence of habitat incompatibility. The mitigation plan recommended grading the marsh plain below the elevations considered optimal for developing mudflat and saltmarsh habitats, to accommodate the natural siltation expected to occur. Although sediment accumulation has not been measured, by all accounts it does not appear that the expected siltation is occurring at the mitigation site. In addition, The anticipated hydrology described in the mitigation plan has not developed at this site, with the resulting hydrology giving rise to the apparent habitat instability.
The concerns over creating mudflat habitat in a historic saltmarsh are discussed by ABA Consultants (1992), who state that "the [Moss Landing South Harbor] mitigation plan was developed by an environmental consultant without regard for the best local and regional wetland restoration needs... Sandflat and channel habitat were created by digging into an historical and degraded pickleweed marsh... A large hole in the marsh was eroded by tractors in several weeks, adding to the overall loss of this natural habitat... The resulting channels are now being enlarged by tidal and wave action and even more of the wetland is being eroded. Nature constructed lush vegetated marshes along the channel of the old river, this is the obvious habitat to restore and enhance." These statements emphasize the need for all mitigation project proponents and reviewers to consider the landscape setting of the mitigation project.
This case demonstrates that despite CCC staff's best intentions to write a permit with conditions that would improve the mitigation project's chances for success, the fundamental requirement for ecological soundness cannot be overlooked. The lack of follow-through with appropriate remedial action, which was stipulated in the permit and the mitigation plan, only further compounded the difficulties associated with the mitigation project. Although the monitoring reports do not provide a clear assessment of performance in relation to all established standards, there were indications the overall project was not on a path to achieving the stated goals. Yet the project proponent continued to act in good faith, making an effort to comply with the permit conditions. This is an awkward position for CCC staff: at what point should the regulatory agency require remediation or substantial change to a mitigation project that may not be working? Unfortunately, no general response to this question exists. The answer will largely depend on the specific project. In the case of this project, there were direct indications of local concern as early as 1992 (e.g., ABA Consultants, 1992). These concerns should have been enough to alert CCC staff to a potential problem. Meetings with the concerned individuals and the project proponent could have served as a forum for developing appropriate alternatives.
This case study illustrates how specific procedural and ecological factors yield a situation that deviates from the "ideal process" described in this document. However, this case study provides useful guidance to future projects: 1) a realistic and appropriate project design is as important as any other element of a mitigation project; and 2) follow-through is critical to achieving success. The key here is that appropriate monitoring and remedial action must be undertaken if the site is not performing as expected, or not progressing toward the goals; in this case, the restoration of an ecologically similar saltmarsh ecosystem. Although the high abundance of birds at the mitigation site exceeds the applicable performance standard, the goal was to restore mudflat and saltmarsh habitats that are ecologically similar to adjacent habitats. That goal remains unfulfilled.
CHECKLIST OF INFORMATION INCLUDED IN THE PERMIT FILE AND THE MITIGATION PLAN FOR THE MOSS LANDING SOUTH HARBOR MITIGATION PROJECT
|
Included |
Omitted |
|
|
X |
Executive Summary | |
Project Description | ||
|
X |
Project location, maps (including aerial photos) | |
|
X |
Project impacts | |
Adversely Impacted Site | ||
|
X |
Ecological assessment of the habitats, functions, and values potentially lost or affected | |
|
X |
Plants (species list) | |
|
X |
Plants (special status species) | |
|
X |
Animals (species list) | |
|
X |
Animals ( special status species) | |
|
X |
Exotic Species (plant and/or animal) | |
|
X |
Water regime/Hydrology | |
|
X |
Water quality | |
|
X |
Soils/Substrate | |
|
X |
Buffers/Surrounding Habitats/Surrounding Land Use | |
Mitigation Goals, Objectives, and Performance Standards | ||
|
X |
Specific Goals (statements of project purpose and expected outcome) | |
|
X |
Specific Objectives (specific actions, or steps taken to achieve the goals) | |
|
X |
Performance standards: quantitative criteria to assess the attainment of goals/objectives | |
|
X |
Time frame: statement of period over which attributes must be shown to be present | |
|
Mitigation Site | ||
|
X |
Ecological assessment of the existing habitats, functions, and
values potentially lost | |
|
X |
Salvage plan (conserves plants and animals from the affected and/or mitigation site) | |
|
X |
Site description, project concept drawing | |
|
X |
Design Rationale | |
Site Plan and Design | ||
|
X |
Site survey and topography | |
|
X |
Specific
design elements and construction methods for hydrology | |
|
X |
Specific design elements and
construction methods for soil | |
|
X |
Specific design elements and
construction methods for ground elevation changes | |
|
X |
Specific design elements and construction methods for buffer areas | |
|
X |
Specific design for vegetation (species composition, exotics removal, sources of seeds) | |
|
X |
Potential Problems and Remedial Measures (responsible entity) | |
|
X |
Long-term Maintenance requirements | |
Monitoring Program | ||
|
X |
Hydrology | |
|
X |
Soils | |
|
X |
Water quality | |
|
X |
Plants | |
|
X |
Animals | |
|
X |
Success criteria for physical and chemical attributes | |
|
X |
Success criteria for biological
attributes
| |
|
X |
Timetable for reporting monitoring results | |
Implementation Schedule | ||
|
X |
Construction schedule | |
|
X |
Monitoring schedule |
MOSS LANDING SOUTH HARBOR PERMIT FILE REVIEW
|
PERMIT NUMBER: 3-88-47 |
APPLICANT: Moss Landing Harbor District |
STAFF ANALYSTS: Hyman |
|
PERMIT APPROVAL DATE: 7/89 |
PROJECT START DATE: 10/89 |
PROJECT COMPLETED DATE: ? |
|
Wetland Mitigation project: (X) Yes ( ) No |
Wetland Restoration project: ( )Yes ( ) No | |
LOCATION OF ADVERSELY IMPACTED SITE West bank of South harbor | COUNTY: Santa Cruz | CITY: Moss Landing |
|
DESCRIPTION OF AREA AFFECTED: 0.35 acre of mudflat impacted to construct a bulkhead 1,300 feet along the west bank of south Harbor, below Sandholdt Road. This construction would involve the placement of 5,500 yards of rock rip-rap for shoreline protection, with associated demolition, dredging, fill, and spoils disposal in mudflat habitat. | ||
LOCATION OF MITIGATION/RESTORATION SITE: South harbor Moss Landing | COUNTY: Santa Cruz | CITY: Moss Landing |
|
ACRES MITIGATED OR RESTORED: 0.35 acre of mudflat lost at the bulkhead site was replaced by 1.05 acres of mudflat at the mitigation site, and 1.4 acres of saltmarsh disturbed by the unauthorized grading and fill at the mitigation site was restored, at the same site. | ||
|
SUMMARY OF PROJECT, INCLUDING WETLAND ACRES, HABITATS, AND FUNCTIONS AFFECTED AND PROPOSED MITIGATION: The Moss Landing Harbor District applied for a coastal development permit (CDP 3-88-47) to construct a bulkhead 1,300 feet along the west bank of south Harbor, below Sandholdt Road. This construction would involve the placement of 5,500 yards of rock rip-rap for shoreline protection, with associated demolition, dredging, fill, and spoils disposal, adversely impacting approximately 0.35 acre of mudflat habitat. The permit application of the bulkhead project was suspended in June 1988, however, when the CCC issued a "Stop Work" order to the Moss Landing Harbor District for unauthorized grading and filling of wetland area along the Old Salinas River near the proposed bulkhead site. Three acres of old dredge ponds and adjacent berms were re-graded to a flat topography. Several truckloads of trash were removed from an area occupied by transients. This activity was considered a violation because no coastal development permit or Section 404 permit had been issued for this work, as required by the Coastal Act and the Clean Water Act respectively. The COE determined that 1.4 acres of the graded area had been jurisdictional wetland under Section 404 of the Clean Water Act. In order to resolve this violation, Moss Landing Harbor District was required to mitigate for the impacts of the unauthorized grading and fill by fully restoring the saltmarsh habitat. The Moss Landing Harbor Wetland Mitigation Plan written in 1989 by Jones and Stokes Associates, Inc., proposed to mitigate for the loss of 0.35 acre of mudflat at the proposed bulkhead site and to restore 1.4 acres of saltmarsh disturbed by the unauthorized fill. Mitigation for both sites would occur at the unauthorized fill site. | ||
Mitigation Attributes:
|
TYPE OF MITIGATION PROJECT: (X) Restoration (X) Creation (X) Enhancement (X) In-kind ( ) Out-of-kind |
|
ACREAGE FOR EACH TYPE IF MORE THAN ONE : Mitigate for the loss of 0.35 acre of mudflat at the proposed bulkhead site and restore 1.4 acres of saltmarsh disturbed by the unauthorized fill. Mitigation for both sites would occur at the unauthorized fill site |
|
|
MITIGATION CONDUCTED: (X) On-site ( ) Off-site |
IF OFF-SITE, RELATIVE LOCATION OF IMPACT SITE VS. MITIGATION SITE (I.E., JURISDICTION, WATERSHED, ETC.): |
MITIGATION RATIO ACRES MITIGATED: ACRES AFFECTED Bulkhead site: 3:1= 1.05: 0.35 Unauthorized fill site: 1:1 = 1.4: 1.4 |
TYPE OF RESTORATION PROJECT: ( ) Restoration ( ) Creation ( ) Enhancement |
ACREAGE FOR EACH TYPE IF MORE THAN ONE: see above |
IS PRESERVATION/ACQUISITION A PROJECT COMPONENT? ( ) Yes (X) No |
IF YES, DESCRIBE WHAT IS BEING PRESERVED OR ACQUIRED, WHERE IT IS LOCATED, THE COSTS AND FUNDING SOURCES AND WHO WILL ASSUME RESPONSIBILITY: |
WAS THERE AN ECOLOGICAL ASSESSMENT OF THE ADVERSELY IMPACTED SITE BEFORE CONSTRUCTION OR ALTERATION? (X) Yes ( ) No |
IF SO, LISTS THE REPORTS, CONCLUSIONS OF THE SITE EVALUATION: One of the conditions required in the CDP 3-88-47 was "a pre-construction survey of intertidal habitat to be lost." In 1985 an Intertidal Invertebrate Study was conducted and concluded that the area was extensively modified for human use and utilized by few invertebrates. Additionally in 1985, an Environmental Assessment of the site was performed by the COE, which described the potential impacts to the site. In 1988 an Expanded Initial Study was conducted. Field sampling characterized the proposed bulkhead site as rocky to silty-sand substrate with accumulations of human generated debris. This report included an invertebrate study which stated that "although diversity was relatively high, low species density indicates that this is not high quality habitat." |
WAS THERE AN ECOLOGICAL ASSESSMENT OF THE MITIGATION SITE BEFORE CONSTRUCTION OR ALTERATION? ( ) Yes (X) No |
|
IF SO, LISTS THE REPORTS, CONCLUSIONS OF THE SITE EVALUATION: No ecological assessment of the unauthorized fill area was performed prior to the grading and filling activity, however, the Mitigation Plan (1989) provided a characterization of the habitat lost at the unauthorized fill site. The site was generally described as having contained areas of undisturbed tidal saltmarsh and moderately disturbed marsh and upland. Common plants at the site had included pickleweed, saltgrass, and other marsh vegetation. This type of vegetation compliment remains in large areas of high quality salt marsh immediately south of the fill site and elsewhere in the vicinity. Common mammals and birds likely to use the site were listed. |
WAS THERE AN ECOLOGICAL ASSESSMENT OF A REFERENCE SITE BEFORE CONSTRUCTION OR ALTERATION? (X) Yes ( ) No Control sites located in adjacent saltmarsh area. |
WERE GOALS AND OBJECTIVES LISTED IN THE APPLICATION MATERIALS? (X) Yes ( ) No |
IF SO, LIST THE GOALS AND OBJECTIVES: |
GOALS: Stated in 1990 revegetation and monitoring plan:
|
|
OBJECTIVES: Stated in 1989 mitigation plan:
|
WERE PERFORMANCE STANDARDS FOR ASSESSING ATTAINMENT OF EACH GOAL/OBJECTIVE LISTED? (X) Yes ( ) No |
IF SO, LIST THE PERFORMANCE STANDARDS, OR SUCCESS CRITERIA: Performance standards (stated in the 1989 mitigation plan):
The 1990 revegetation and monitoring plan report stated "a success criteria of 90% survival after one full year of growth after installation shall be established for all installed plants." This standard applies to all of the plant types mentioned above. |
WAS A MONITORING PROGRAM INCLUDED? (X) Yes ( ) No |
LENGTH OF MONITORING PROGRAM: 5 years |
|
WHEN ARE MONITORING REPORTS DUE? Annually |
|
BRIEFLY LIST THE PARAMETERS TO BE MONITORED: Vegetation cover and composition. The identity and relative abundance of all plants will be recorded. Potential problems that may require remediation will be monitored, such as erosion, or failure of plants to become established. The monitoring program also included monitoring of birds and benthic fauna at the mitigation and control sites. |
EVALUATION OF PERFORMANCE: |
DO SUCCESSIVE MONITORING REPORTS DOCUMENT PERFORMANCE OF THE PROJECT? (X) Yes, but only for birds ( ) No |
IF YES, DOES THE DATA INDICATE THAT THE SYSTEM IS EVOLVING TO MEET THE GOALS, I.E., IS THE PERFORMANCE IMPROVING? The Appendix of the 1990 report discusses the preliminary results of the bird monitoring. "Waterbird species richness on the restoration site is greater than elsewhere along the Old Salinas River." These results are corroborated in the 1991 monitoring report. The 1991 monitoring report also states that the abundance of benthic organisms on the restoration site approximates abundance levels documented in nearby control sites. The 1992 monitoring of shorebirds also indicates the high habitat value of the mitigation site for bird foraging habitat. While the 1994 data for these two biotic attributes is inconclusive, the field site evaluation corroborated the apparent trend of increasing performance of the restored mudflat as habitat for shorebirds. Such a trend is not evident in the establishment of vegetation at the mitigation site. The data reveals that while some areas of the mitigation site show high plant survival rates and recruitment, plants in the southern portion of the site experienced die-off and slower rates of growth. Thus, some areas of the mitigation site do not meeting the 90% success criteria for installed plants. The evaluation of plant performance is not included in any monitoring report currently available. |
MOSS LANDING SOUTH HARBOR MITIGATION SITE EVALUATION
|
DATE OF VISIT: 12/7/94 and 2/5/95 |
EVALUATORS: Hymanson, Hyman, Kingma, Monowitz |
Fill in this portion of the form before the site visit
Project Information:
PROJECT NAME: Moss Landing South Harbor Mitigation Project | |||
|
PERMIT NUMBER: 3-88-47 |
ANALYSTS: Hyman | ||
|
MITIGATION PROJECT LOCATION: South Harbor, Moss Landing |
CITY: Moss Landing |
COUNTY: Santa Cruz | |
|
|
|
| |
PERMIT APPROVAL DATE: 7/89 | CONSTRUCTION START DATE: 10/89 |
PROJECT COMPLETION DATE: ? | |
|
(X) Mitigation or ( ) Restoration | |||
|
ADVERSELY IMPACTED AREA: | |||
|
ACRES 0.35 acre | |||
|
HABITAT TYPE: Rocky to silty-sand mudflats | |||
|
MITIGATION SITE: | |||
|
Acres: | ENHANCED: 1.1 acres (conversion) |
RESTORED: 1.4 acres | CREATED: unknown amount |
|
Habitat type: |
1.4 acres of saltmarsh restored or created at the unauthorized fill site. In addition, 1.1 acres of adversely impacted saltmarsh was converted to mudflat habitat. | ||
|
RESTORATION SITE: | |||
|
Acres: | ENHANCED: |
RESTORED: |
CREATED: |
|
Habitat type: | |||
|
PROJECT GOALS AND OBJECTIVES (AS STATED IN THE FILE DOCUMENTS) | |||
|
GOALS:
| |||